F10 Notification of Projects to HSE
Information regarding F10 notification of projects to the HSE and what you need to do:
Commercial Clients:
It is your duty as Client to notify the HSE of a project.
Click on the link below to notify the HSE of a project if the following criteria will be met:
- Project will last more than 30 working days and have more than 20 workers working simultaneously at any point, or
- The project will exceed 500 person days
https://www.hse.gov.uk/forms/notification/f10.htm
Domestic Clients:
It is the Contractor / Principal Contractor’s duty to notify the HSE of a project (Unless it has been agreed that the Principal Designer will take on these duties).
Click on the link below to notify the HSE of a project if the following criteria will be met:
- Project will last more than 30 working days and have more than 20 workers working simultaneously at any point, or
- The project will exceed 500 person days
https://www.hse.gov.uk/forms/notification/f10.htm
NOTE: The F10 must be displayed in the construction site office.